Timeline
- The colored bars on the top of the timeline represent the phases of the project and provide a percent complete of each phase.
- The Green markers represent the dates when each of the campuses GO LIVE with Bi-weekly payroll.
- The Red markers represent the dates of competing projects.
Bi-weekly payroll 4-campus target timeline explained
- Acquisition: 114 days between January 2020 - April 2020, with 80% completion estimated April 2020.
- Planning: 477 days between March 2020 - February 2021, with 30% completion estimated April 2020.
- Implementation: 354 days between March 2020- February 2021, with 10% completion estimated April 2020.
- Closeout: 61 days between March 2021 - April 2021.
- Sustainment: 122 days between March 2021 - June 2021.
Milestones
December 18, 2020 – BL & GF GO LIVE
February 26, 2021 – BZ & HV GO LIVE